The same old problem with a brand new solution. A completely replaced controls system. 5 panels with all they contain. Under 7 days’ downtime. 100% production on day 1.
Old equipment is a staple on the plant floors of any manufacturer that has been running for more than a decade. Maintenance teams meticulously maintain these machines. Eventually the controls components (PLCs, drives, starters, etc.) fail and they get replaced. Then one day, the last spare gets used up and the distributor no longer carries the parts. Waiting for the “right time” for a controls upgrade, you’re left relying on eBay and repair shops to keep the plant up and running.
Sound familiar? How much is on the line when your aging machine goes down and replacement parts are no longer a phone call away?
This was the situation of one our customers machining engine blocks. Several of their machines that perform rough-cut operations were approaching 20 years old. They were very concerned about the looming possibility of one of their PLC’s or drives failing and not being able to get a replacement. Millions of dollars in lost production time were on the line.
After carefully weighing replacement vs retrofit, this customer turned to Patti Engineering to develop a retrofit solution that would meet their requirements. Replacing 5 control panels, with 5 PLCs, 8 servo drives and motors, cabling, and cable carriers per machine was a tall order. Doing it with under 7 days of downtime – some might even say impossible. The customer had received other estimates of up to 6 weeks of downtime!
The Patti Engineering team went with a Siemens solution for this controls upgrade. This drastically cut down onsite install, debug, and testing to meet the time frame. Five PLCs were replaced with a single Siemens 1518F processor (the “Cadillac” of the new Siemens 1500 series PLC line). Sinamics S120 servos paired with Simotics servo motors provided control for the machining process as well as the gantry transfer system to smoothly handle engine blocks weighing over a ton. A dozen ET200sp remote I/O racks were placed directly on the machines, greatly reducing cabling. Profinet ties the whole system together through Scalance industrial ethernet switches.
But how do you get all this hardware installed, programmed, and running production in under 7 days? Our engineering team employed several strategies to make this quick turnaround. We worked closely with our panel shop to design a modular panel design that could be installed and wired quickly in the field. As the panels were built, our team did comprehensive panel testing, networking configurations, and drive setup in the shop. The key to the whole operation though was creating a digital twin.
A digital twin is a digital representation of a physical process. We used Siemens PLCSim Advanced to create a series of programs, which identically matched the physical machine and how it operates. We were then able to test and debug 95% of our machine programming before we installed a single panel onsite. This made our 3-4 day window of debugging and testing an obtainable goal.
As soon as the machine was turned off and handed over to Patti Engineering, a team of over 30 engineers, electricians, and technicians descended on the work site. Working 24 hours a day , they removed and replaced every control cabinet, cable, cable carrier, and servo motor on the machine. Testing and debug then went very smoothly due to the virtual debug and testing, enabled by the digital twin. Production started up on schedule and the machines were producing at 100% from day 1.
Our customer benefited from having an entire, brand new, upgraded controls system up and running production in 7 days – less than a quarter of the time others had estimated via traditional commissioning. In addition, they now have machines that run faster, recover easier, and have less downtime than they have ever had in their 20-year history.
Many manufacturers are hesitant to retrofit their machinery because they can’t afford the risk of extended downtime. They also can’t rationalize replacing machines that are in great shape mechanically. However, running machinery on borrowed time is never a good solution. An experienced systems integrator, such as Patti Engineering, can work around customer requirements and utilize modern design techniques to dramatically reduce the risk and downtime.
Texas Director of Operations
Hired in 2008, Nick Hitchcock has served in several engineering and management roles in the company’s Austin office. Starting out at the Michigan office, and moving to Texas in July 2010, he now serves as the Director of Texas Operations.Sometimes a client needs a solution to a problem, but does not know what or how to go about developing one. Patti Engineering offers engineering...
Patti Engineering utilizes trusted advisor status and proven expertise to research and develop a solution for an integral verification station for a medical device manufacturer.
Take the first step towards optimizing your business operations and staying ahead of the competition.